January 2003

Plumbing Costs

This bulletin addresses plumbing costs common to commercial and industrial interior improvements. The costs presented here are an average of those received in response to a survey of local plumbing contractors.The pricing is presented in a "rule of thumb" context; several factors will affect the actual cost on your project. These are: a) project size b) actual conditions on the site c)number of quotes received and d) market forces at the time of bid.

The basis of the following line items #1 through # 8 is: A sawcut of a concrete floor connection to an existing sewer line within ten feet of the finished installation location, water supply tapped from within the building and reasonably close at hand,venting, furnishing and installing the fixture, backfill of the trench, compaction doweling of trench edges and concrete placement and finish.

Fixtures: American Standard or equal. Note that for items (3) through (7) pricing is predicated on a minimum of (1) toilet (either # 1 or # 2)being installed. - if a toilet is not being installed then $1,050.00 must be added to the unit costs of items (3) through (7). If you have a general contractor managing your project all pricing will be slightly higher.

No.
Description
Unit
Unit cost
1
Floor mounted tank toilet
Each
$ 2,350.00
2
Floor mounted toilet with flush valve (no tank)
Each
$2,650.00
3
Wall hung lavatory with ADA faucet
Each
$1,000.00
4
Wall mounted urinal with flush valve
Each
$1,400.00
5
Stainless steel bar/lunchroom sink and faucet
Each
$1,400.00
6
Floor drain
Each
$1,250.00
7
Floor sink
Each
$1,400.00
8
Handicapped shower enclosure with seat, pre-fabricated
Each
$4,600.00
9
Emergency eyewash/shower station, no waste line required
Each
$950.00
10
Adder for additional distance from fixture to sewer (exceeding 10 l.f.) for additional concrete cutting, patching and laying of sewer line 
L.F.
$49.00
11
Electric water heater, 6 gallon ( excludes elec. connection)
Each
$650.00
12
50 Gallon heater (excludes elec. connection)
Each
$2,000.00
13
Under sink "point of use" water heater(excludes elec. connection)
Each
$425.00
14
Condensate connection to a.c. unit
Each
$300.00
15
Condensate line on roof, run to roof drains
L.F.
$4.50
16
1" gas line - installed on roof
L.F.
$8.50
17
2" gas line - installed on roof
L.F.
$13.00
18
1" water line installed along underside of roof
SF
$10.00
19
1" CDA - Clean dry air- (nitrogen purged) 
L.F.
$14.00