What I hate about change orders

Few construction projects can be completed without change orders. A change order is the means to bridge the intent of the design and the reality of the field. The most palatable of change orders are classified as 'Express Change orders'. These change orders usually consist of deletions or additions to the contract and are priced by the contractor in advance of the owner's acceptance. They are clear-cut, value adding, contract governed and uncontestable.

Unlike 'Express Change Orders' directed by the owner on a voluntary basis, the second class of change order: 'Constructive Change Orders' arise during the course of work from circumstances that were unforeseen by participants in the project at the time of bid and force performance of the contractor above and beyond the stipulations of the contract.

What I actually dislike most are change orders falling into the class: "Constructive Change Orders of the third kind. "

Kinds of Constructive Change Orders

I. Concealed Conditions is a contractual term describing unavoidable conditions discovered or emerging after the contract is executed.

  • Existing sewer line undersized or deteriorated
  • Existing electrical wiring not to code
  • HVAC equipment thought be working but discovered to be unusable
  • Deficient seismic restraints/connections not apparent during design or bidding.
  • Columns or Conduits concealed in walls
  • Human remains or artifacts found during excavations
  • Emergencies - threats to life or property.

Concealed conditions are, fortunately, self evident, easy to document and most owners and contractors will be able deal with them evenhandedly within the terms of the contract.

II. Defective plans
In every construction contract, where he has hired a third party design professional, the owner implies and warrants that the plans and specifications are accurate and sufficient enough to build the project. Although cities check the plans prior to issuing the permit they are not concerned with the intent of the design so much as with compliance with the building codes.

Being off-site, plan checkers are unable to compare the drawings with the actual conditions at the site. Frequently errors or omissions in the plans are not discovered until the inspector arrives – by which time the cost of correcting errors may have increased.

Even in the TI business, working in existing buildings, we see defective plans –and the architect is often not at fault. Frequently the designer is given outdated or inaccurate information by the owner or a tenant upon which the design is based. Other examples of defects are:

  • Missing or inaccurately specified handicapped access features
  • Fire rating, exiting , seismic restraint, storage issues
  • Code interpretation differences between architect and jurisdiction
  • Insufficient allowances provided by the contract due to vague criteria on the plans
  • Construction details unworkable in the field
  • 'Red Lined' plans will almost certainly create change orders if the contract has been signed prior to submittal to the city and receipt of comments.
    Most professionals in the design industry own up to their errors and will advise the owner to issue a change order to the contractor to correct such defects. Sophisticated owners generally rely on experienced design firms to mitigate these problems.

III. Owner caused delays and sequencing changes The 3rd Kind
In every construction contract there are duties for which the owner is obliged. They could be as simple as making the space available by a certain date or be very complex with the owner furnishing salvaged items for re-installation and/or having his own subcontractors perform schedule critical activities within the order of work. Some potential problems with owner performed work:

  • Delays by owner's subs in performing their work within the schedule window provided by the GC.
  • Incomplete or damaged items provided to the GC by the owner for installation which invariably causes additional cost and time delay

Sequencing change orders arise when the contractor is directed to perform in a manner not customary for the industry and, more importantly, not addressed in the contract. In bidding for and subsequently fulfilling his contract, the contractor has the expressed duty and implied right to direct the work in the manner he deems most beneficial to himself and, absent any provision to the contrary in the bid documents, bids and performs the work accordingly.

  • A very common sequencing problem arises from the owner's direction to start work in advance of the permit being issued - which in many instances saves time. However, in some cases the cities can take too long in the plan review process and delay completion of a job already started – and stopped - pending the permit being issued and subsequent inspections. The contractor would experience an increase in his costs because the project could not be completed within the time the contractor could have finished it had the permit been issued prior to the start of work or issued within his critical window.
  • Sometimes project delays, caused for any of the reasons in this article, are simply untenable for the owner or tenant and a portion (or all) of the project requires acceleration to meet the original completion date. Acceleration might involve overtime for the construction team, finishing portions of the work out of the sequence intended, or both.

These 'Change orders of the Third Kind' are the thorniest ones, with the potential of creating an adversarial relationship between a contractor and his owner/client. Prevention is the best solution for all parties:

  • Maintenance of a master schedule showing delays and accelerations and their causes
  • Weekly propagation of a rolling schedule to the owner's subs as well as the general contractor's
  • When using salvage materials and equipment the owner must survey those items for entirety and fitness as soon as possible, especially if their replacements require lead time.

A good contracting practice is to establish in the contract a provision to resolve any disputed change order amounts on a T&M basis. Such a provision would stipulate (in advance) the general contractor's markup on subcontracts, materials and equipment, rates for supervisory labor and general conditions (phone, trailer, insurance). With this provision in place the work could be done on a T&M basis with a 'not to exceed' threshold where practical.

Although the best of plans can go awry the more time spent up front in surveying the condition of existing items to be re-used, site investigation, conferring with city planners and plan checkers, stipulating phasing concerns with bidders and having contractors bid city approved plans will minimize the risk of change order claims.

This boat probably belongs to a contractor (with a sense of humor) who did quite well on a job that, for one or more of the reasons listed above, widened far beyond the scope of the 'original contract'; - name on the dinghy.

TiCon - You get it on time or you get my car keys - Sam Burkhouse

We Never Charge For Quotations From Your Plans And Specs
Pre-Construction Services Available

info@ticon.com