Conditional Use Permits - Process and timeline

Since the first (1860) case in New York City, ordinances restricting property use, based on the health, welfare and safety of citizenry, have been upheld by the Supreme Court of the United States.

A CONDITIONAL USE PERMIT (CUP) allows a city or county to consider special uses which may be essential or desirable to a particular community, but which are not allowed as a matter of right within a zoning district, through a public hearing process. A conditional use permit can provide flexibility within a zoning ordinance. Another traditional purpose of the conditional use permit is to enable a municipality to control certain uses which could have detrimental effects on the community. Consideration of a CUP is a discretionary act. A CUP application tendered by a project proponent is considered at a public hearing and, if approved, is generally subject to a number of pertinent conditions of approval.

Every City has a standard procedure for the submission and review of an application for CUP. The following model is taken from the City of San Jose's web publication. The duration of the steps is based on an application for use and an interior improvement.Note that the CUP must be granted prior to submission of drawings to the building department for permit. The lesson for clients is that the requirement for a Use Permit will easily add 90 days to the overall timeline.

Planning Steps
Days
Alternate activity
Planning application submitted to City
Preliminary project review by City staff and determination of application completeness
10
If incomplete then return above
Application deemed complete, process and paperwork continues
15
Planning Commission (PC) decision: CEQA Exempt
15
Staff review of project for code compliance
7
Development review board meets; conditions of approval proposed
15
Staff report prepared, notifications sent
10
PLANNING COMMISSION HEARING
1
Planning Commission approves,      
5
or
Refers to City Council
10 day decision Appeal Period
10
an unusual step
May file building permit application - or not, if there is no construction
Appeal filed and hearing set
Project timeline without serious issues or re submittal (total)
88
.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The trade contributor for this newsletter, Russ Gamble - Architect, suggests the following "Ten Commandments" for securing a change of use on a property.

1 Check with the Planning Department if use is permitted in the subject zoning district. 
2 Schedule a neighborhood meeting for input and respond with real solutions.
3 Determine at initial meeting with Planning whether an environmental impact report (CEQA) will be required.
4 Discuss with Planner the permit and zoning options available, such as “overlay” districts and “conditions of approval,” as may be necessary.
5 Make certain permit application is complete the first time it is submitted, otherwise the project will be delayed 10-14 days plus correction timeline.
6 Permit application submittal should include clear, easily understood graphics (plans, elevations), the use of color is an asset.
7 Meet with Planning Commissioners individually to explain project and ask for feedback.
8 Check with Project Planner weekly or so to find out if staff report/recommendation is complete and obtain a copy before the public hearing.
9 Stay in contact with Project Planner regarding when notices of public hearing are sent out to neighbors and learn date of hearing.
10 Be prepared to make a presentation and/or answer questions at the public hearing, refer to graphics as available.